Handover of body-in-white to the paint shop (P2M.02.01)

Process step · level L4 · last produced from the model on 12 Sep 2026

Produced from the model. This page is generated from the process model in TAOM Process Studio. Sections marked ↑ are overwritten on every run; freely written paragraphs are kept.

What belongs to it

What happens beforeBody-in-white is welded and inspected (P2M.01.06). The inspection record exists, rework is complete.
What happens hereHandover to the paint shop: visual inspection, labelling, posting of the stock transfer, release of the conveyor.
What happens afterPre-treatment and dip priming (P2M.03.01).

Header data

TAOM identifierP2M.02.01 · immutable
LevelL4 – process step
Process areaProduction · surface
OwnershipHead of body shop
ContributingPaint shop, maintenance, quality assurance
Process indicatorHandover lead time < 12 minutes
SystemsERP (stock management), MES (conveyor), QA system
Cluster / capabilityBody manufacturing
Statusreleased
Version3.2 · produced on 12 Sep 2026

1 · Process overview (L4)

The body-in-white leaves the body shop and passes to the paint shop. Before handover it is visually inspected, labelled, and the stock transfer is posted. Only after the posting does the conveyor release the section. The handover counts as completed once posting and release exist and the label on the vehicle is legible.

4phases
17steps
6requirements
3WRICEF objects

2 · Process model (TAOM Process Studio / BPMN)

Embedded in the TAOM viewer – the same display as in the editor, without editing. The model remains the source; here it is only shown.

Process Studio Viewer (BPMN v1.18.0) www.taom.ai
Model stateBPMN 2.0 · version 3.2
Origin of the displayTAOM Process Studio · provenance seal verified
Editingonly in the editor – this page displays, it does not own

3 · Dependencies (required scope items)

IdentifierDescriptionTypeeStatus
P2M.01.06Body-in-white welded and inspectedPredecessorreleased
P2M.03.01Pre-treatment and dip primingSuccessorin progress
I2M.04.02Stock management interim storageSystem sidereleased

4 · Assumptions & decisions

IdentifierSubjectDecisionDateStatus
ENT-014Labelling on the vehicleAdhesive label instead of tag – machine readable14.07.2026decided
ENT-021Posting momentPosting when leaving the hall, not on arrival02.08.2026decided
ANN-006Buffer placesAssumed: 12 places suffice at a cycle time of 68 sopen

5 · Security & permissions

RolePermissionSystemAccess
Operator handoverCreate postingERPgranted
Shift managementCancel postingERPgranted
Quality assuranceRecord inspection resultQS-Systemrequested
MaintenanceRelease conveyorMESgranted

6 · Organisational structure & master data

All names on this page are invented.

LevelAreaRoleNameStatus
1Plant managementSponsorMarlen Ostbergconfirmed
2Body shopProcess ownershipHenrik Falknerconfirmed
2Paint shopProcess ownershipSina Brauwaldconfirmed
3Quality assuranceFunctional reviewTomas Ehrlicherconfirmed
3MaintenanceConveyorNele Wingertunder review
3IT / ERPStock managementRoland Sikorraconfirmed
4Occupational safetySite walkYasmin Terwelprejected
4Works councilConsultationIngmar Loetschopen

7 · Country rollout

Legal entityCountryWaveDeviation
Nordwerk GmbHGermanyWave 1
Nordwerk Ibérica S.L.SpainWave 2Label bilingual
Nordwerk CZ s.r.o.CzechiaWave 3Buffer places differ

8 · Value case

LeverMeasureTodayTarget
Less search time at handoverHandover lead time16 min12 min
Fewer incorrect postingsCorrection postings per week23< 5
Less rework caused by mix-upsCases per month40

9 · Phases & steps

Produced from the model: one epic per phase, one issue per step. The identifier stays the same across all runs.

PhaseStepIdentifierIssueStatus
PrepareTake over inspection recordP2M.02.01.01NWK-1042done
PreparePrint and attach labelP2M.02.01.02NWK-1043done
InspectVisual inspection of surfaceP2M.02.01.03NWK-1044in progress
InspectRecord deviationP2M.02.01.04NWK-1045in progress
PostPost stock transferP2M.02.01.05NWK-1046open
Hand overRelease conveyorP2M.02.01.06NWK-1047open

10 · Testing and traceability

IdentifierTest caseRiskControlResultIssue
TC-0311Label machine readableRISK-004CTRL-009passedNWK-1101
TC-0312Posting without inspection record is rejectedRISK-001CTRL-014 four-eyespassedNWK-1102
TC-0313Release only after postingRISK-001CTRL-015open – retestNWK-1103
TC-0314Cancellation creates reversal postingRISK-007CTRL-021plannedNWK-1104

11 · Requirements

IdentifierRequirementTypeIssueStatus
ANF-118Posting must require an inspection recordfunctionalNWK-0912implemented
ANF-119Label with vehicle and order numberfunctionalNWK-0913implemented
ANF-124Posting response time below 2 secondsnon-functionalNWK-0918in progress

12 · WRICEF objects

TypeIdentifierDescriptionEffortStatus
InterfaceI-014Posting message ERP to MESMaccepted
FormF-006Label body-in-whiteSaccepted
ReportR-022Correction postings per shiftMin progress

13 · References & downloads

ModelP2M.02.01 · BPMN 2.0 · version 3.2
Enterprise modelPlacement in the enterprise model →
Project organisationResponsibility & project organisation →
How this is producedOutbound, return and field ownership →

In operation the same preparation is produced from your model, with your identifiers and your issues – here on taom.ai, in your Confluence or as output to another target system. Invented content here, real structure.

Request a live demo →